The Kentucky General Assembly authorized the Pendleton County project in 2005 and approved its funding in 2006. The total project cost is $11.7 million. The building is approximately 35,000 square feet and was completed in May 2010.
Project Development Board
Pendleton County Judge-Executive Henry Bertram, Chairman
Chief Regional Circuit Judge Robert McGinnis, Vice Chairman
Gary Veirs, Fiscal Court Representative
Michael Redden, Pendleton County Circuit Clerk
The-Late Doug Wright, Kentucky Bar Association Representative
Billy Hatfield, AOC Representative
Ronnie McCall, AOC Division of Capital Construction
Project Completion Team
Construction Manager, Codell Construction Co., Winchester, KY
Architect, CMW Inc., Lexington, KY
Financial Agent, Ross, Sinclaire & Associates, KY
Bond Counsel, Peck, Shaffer & Williams, KY